Because of materials shortages, the scheduled lane closures near the roundabout at Fruitville Road and U.S. 41 have been delayed from Wednesday, Feb. 1 to Friday, Feb. 3 to Sunday, Feb. 5 to Thursday, Feb. 9.
The Florida Department of Transportation has informed the city of Sarasota of lane closures on approach to the roundabout at Fruitville Road and U.S. 41 for the second half of this week. Some of the lane closures will take place during the day.
Access will be maintained for all routes. However, similar to early January when a lane in the roundabout was closed without prior announcement, motorists can expect heavy delays in the area and from the barrier islands.
Access will be maintained for all routes.
The revised schedule is as follows:
Nighttime lane closures Sunday, Feb. 5 through Wednesday, Feb. 7 starting at midnight.
Daytime lane closures from 4 a.m. to 2 p.m. Monday, Feb. 6 through Thursday, Feb. 9.
Crews will excavate existing pavement and prepare the curb pad for concrete.
These lane closures are necessary as crews pour concrete for new median curb and new storm drain inspections.
The Florida Department of Transportation has informed the city of Sarasota of lane closures on approach to the roundabout at Fruitville Road and U.S. 41 for the second half of this week. Some of the lane closures will take place during the day.
Access will be maintained for all routes. However, similar to early January when a lane in the roundabout was closed without prior announcement, motorists can expect heavy delays in the area and from the barrier islands.
Access will be maintained for all routes.
Nighttime lane closures on Wednesday, Feb. 1 and Thursday Feb. 2 include:
Crews will excavate existing pavement and prepare the curb pad for concrete.
Daytime lane closures from 4 a.m. to 2 p.m. Thursday, Feb. 2 and Friday Feb. 3 include:
These lane closures are necessary as crews pour concrete for new median curb and new storm drain inspections.