- November 15, 2024
Loading
The Bradenton Beach Sewer Improvement Project continues, with lane shifts scheduled for this week.
Starting March 18, both lanes of Gulf Drive South will be shifted west between 6th Street South and 8th Street South. The lane shift is expected to continue through late March or early April, according to a press release.
Also during this time, 7th Street South will be closed to traffic. There will be temporary parking on the west side of Gulf Drive South, as well as a free shuttle service for residents and guests of that street.
The $7.1 million project is funded by Manatee County, and will replace and relocate some of the gravity sewer system in South Bradenton Beach.
Construction for this project began in early 2023, and is anticipated to continue until late 2024, according to the project website.